Final Baseline Hydrology Report April 2012
Draft DFHAD (Hydraulic Models) April 2012
Final DFHAD November 2013
Draft Alternatives Analysis Report May 2012
Final Alternatives Analysis Report November 2013
Draft Conceptual Design Report March 2014
Public Meeting March 12, 2014